-Frank B. Gilbreth's multiple construction companies created at least 90 large-scale projects over its span of about fifteen years. This list is likely incomplete and there may be many more minor projects that have escaped discoverable records.+Frank B. Gilbreth's multiple construction companies created at least 100 large-scale projects over its span of about fifteen years. This list is likely incomplete and there may be many more minor projects that have escaped discoverable records, including six references that have not been resolved.
  
-  * //<color blue>Note: the numbering system here is completely arbitrary and used only for convenience and organization of this material. There may be any number of anomalies of actual chronology and undocumented projects.</color>//+  * //<color blue>Note: the numbering system here is completely arbitrary and used only for convenience and organization of this material. There may be any number of anomalies of actual chronology and undocumented projects. I am also attempting to reorder the projects from time to time as more accurate dates and timelines are discovered.</color>// 
 + 
 +<color red>**Table renumbering and restructuring in progress**. Cross-reference lists may not be fully updated.</color> 
 + 
 +^  #  ^ Project  ^ Location  ^ Dates ^ 
 +|  **000** |  //[[P000 | — Early & Unverified Projects —]]//  || 1895-1905 | 
 +|  S-001 | [[P001|Prescott Hall dormitory]] | [[fbglist-geo#cambridge, massachusetts|Cambridge, MA]] | May 1896\\ Sep 1896 | 
 +|  D-002 | [[P002|Webster Building]] | [[fbglist-geo#cambridge, massachusetts|Cambridge, MA]] | 1896 | 
 + 
 +=== Project Number Key === 
 +  * **S** – Standing and in original condition and use 
 +  * **M** – Standing in modified condition or use 
 +  * **N** – Standing and on National Register of Historic Places roster 
 +  * **D** – Demolished 
 +  * **U** – Unknown 
 +  * //Note that dates are summary, the earliest and latest known to be associated with construction.// 
 + 
 +----
  
 ^ ^ Project  ^ Location  ^ Date  ^ ^ ^ Project  ^ Location  ^ Date  ^
-| [[P001|001]] | //[[P001|Unknown]]// | [[fbglist-geo#auburn, new york|Auburn, NY]] | July 1895 | +| 004 | [[P004|Craigie Hall dormitory (masonry work)]] | [[fbglist-geo#cambridge, massachusetts|Cambridge, MA]] | 1897 | 
-| [[P002|002]] | [[P002|Prescott Hall dormitory]] | [[fbglist-geo#cambridge, massachusetts|Cambridge, MA]] | Under construction May 1896\\ Occupancy by Sep 1896 | +| 005 | [[P005|Brimmer Chambers apartments]] | [[fbglist-geo#boston, massachusetts|Boston]] | 1898 | 
-| [[P003|003]] | [[P003|Webster Building]] | [[fbglist-geo#cambridge, massachusetts|Cambridge, MA]] | 1896 | +| 006 | [[P006|Womens' Club building]] | [[fbglist-geo#boston, massachusetts|Boston]] | Contracted Late 1898\\ Completed Mar 1899 | 
-| [[P004|004]] | [[P004|Craigie Hall dormitory (masonry work)]] | [[fbglist-geo#cambridge, massachusetts|Cambridge, MA]] | 1897 | +| 007 | [[P007|Boston Dispensary addition]] | [[fbglist-geo#boston, massachusetts|Boston]] | Dec 1898-99 | 
-| [[P005|005]] | [[P005|Brimmer Chambers apartments]] | [[fbglist-geo#boston, massachusetts|Boston]] | 1898 | +007a| [[P007a |Power Station for Plymouth & Brockton Street Railway]] | Plymouth, MA | Contract May 1901\\ Completed Aug 1901 | 
-| [[P006|006]] | [[P006|Women’s Club building]] | [[fbglist-geo#boston, massachusetts|Boston]] | Contracted 1898\\ Completed 1899 | +| 007b| [[P007b |Freight House for Boston & Albany RR]] | Boston | Contract Aug 1901 | 
-| [[P007|007]] | [[P007|Boston Dispensary addition]] | [[fbglist-geo#boston, massachusetts|Boston]] | 1898-99 | +|  —  |  — //[[gap1899-1902 | Gap of 1899–1902]]// —  ||| 
-| — |  — //[[gap1899-1902 | Gap of 1899–1902]]// —  ||| +| 008 | [[P008|Lowell Memorial Electrical Engineering Laboratory]] | [[fbglist-geo#boston, massachusetts|Boston]] | Contract Jun 1902\\ Completed Aug 1902 | 
-| [[P008|008]] | [[P008|Lowell Memorial Electrical Engineering Laboratory]] | [[fbglist-geo#boston, massachusetts|Boston]] | Contract Jun 1902\\ Completed Aug 1902 | +| 009 | [[P009|Brick Chimney & Powerhouse for Cambridge Electric Light Co]] | [[fbglist-geo#cambridge, massachusetts|Cambridge, MA]] | 1902 | 
-| [[P009|009]] | [[P009|Brick Chimney & Powerhouse for Cambridge Electric Light Co]] | [[fbglist-geo#cambridge, massachusetts|Cambridge, MA]] | 1902 | +| 010 | [[P010|Expansion of Towns Hotel]] | Bellows Falls, VT\\ [now Rockingham] | 1902 | 
-| [[P010|010]] | [[P010|Expansion of Towns Hotel]] | Bellows Falls, VT\\ [now Rockingham] | 1902 | +| 011 | [[P011|Enlarge Power Station Canal]] | Garvin’s Falls, NH | 1902 | 
-| [[P011|011]] | [[P011|Enlarge Power Station Canal]] | Garvin’s Falls, NH | 1902 | +| 012 | [[P012|Extension of Mill for Boston Manufacturing Company]] | Waltham, MA | 1902 | 
-| [[P012|012]] | [[P012|Extension of Mill for Boston Manufacturing Company]] | Waltham, MA | 1902 | +| 013 | [[P013|Factory for Cluett, Peabody & Co (Arrow Shirts) ]] | Leominster, MA | 1902 | 
-| [[P013|013]] | [[P013|Factory for Cluett, Peabody & Co (Arrow Shirts) ]] | Leominster, MA | 1902 | +| 014 | [[P014|3-story Building for Lever Brothers]] | [[fbglist-geo#cambridge, massachusetts|Cambridge, MA]] | 1903 | 
-| [[P014|014]] | [[P014|3-story Building for Lever Brothers]] | [[fbglist-geo#cambridge, massachusetts|Cambridge, MA]] | 1903 | +| 015 | [[P015|“Dove” Paper Mill for Megargee Paper Company]] | Modena, PA | Contract Jul 1903\\ Completed Oct 1903 | 
-| [[P015|015]] | [[P015|“Dove” Paper Mill for Megargee Paper Company]] | Modena, PA | Contract Mar 1903\\ Completed late 1903 | +| 015a | [[P015a|Warehouse for Boston Wharf Co]] | Boston | Contract Apr 1903\\ Completed Nov 1903 | 
-| [[P016|016]] | [[P016|Concrete Dam for Potter Hill Textile Mill]] | Westerley, RI | Contract July 1903 | +| 015b | [[P015b|Factory for Columbian Rope Co]] | [[fbglist-geo#auburn, new york|Auburn, NY]] | 1903-04 | 
-| [[P017|017]] | [[P017|Moses Taylor Hospital]] | West Seneca, NY\\ (Now Lackawanna) | Contract Oct 1903 | +| 016 | [[P016|Concrete Dam for Potter Hill Textile Mill]] | Westerley, RI | Contract July 1903 | 
-| [[P018|018]] | [[P018|Irons & Russell Building]] | Providence, RI | Contract Oct 1903\\ Completed 1904 | +| 017 | [[P017|Moses Taylor Hospital]] | West Seneca, NY\\ (Now Lackawanna) | Contract Oct 1903 | 
-| [[P019|019]] [[P019|Factory for Columbian Rope Co]] [[fbglist-geo#auburn, new york|Auburn, NY]] | 1903-04 +| 018 | [[P018|Irons & Russell Building]] | Providence, RI | Contract Oct 1903\\ Completed 1904 | 
-| — |  — //[[gbf1903 | Great Baltimore Fire, Feb 1903]]// —  ||| +| 019 | See 015b ||| 
-| [[P020|020]] | [[P020|Piper Building]] | [[fbglist-geo#baltimore, maryland|Baltimore, MD]] | Contract Apr 1904 | + —  |  — //[[gbf1903 | Great Baltimore Fire, Feb 1903]]// —  ||| 
-| [[P021|021]] | [[P021|3-story Warehouse]] | [[fbglist-geo#baltimore, maryland|Baltimore, MD]] | Contract Apr 1904 | +| 020 | [[P020|Piper Building]] | [[fbglist-geo#baltimore, maryland|Baltimore, MD]] | Contract Apr 1904 | 
-| [[P022|022]] | [[P022|6-story Warehouse for John Duer & Sons]] | [[fbglist-geo#baltimore, maryland|Baltimore, MD]] | Contract May 1904 | +| 021 | [[P021|3-story Warehouse for Mary Sanders ]] | [[fbglist-geo#baltimore, maryland|Baltimore, MD]] | Contract Apr 1904 | 
-| [[P023|023]] | [[P023|Building for DA Sargent/Normal School of Physical Education ]] | [[fbglist-geo#cambridge, massachusetts|Cambridge, MA]] | Completed Aug 1904 | +| 022 | [[P022|6-story Warehouse for John Duer & Sons]] | [[fbglist-geo#baltimore, maryland|Baltimore, MD]] | Contract May 1904 | 
-| [[P024|024]] | [[P024|Ray Memorial Building / Franklin Public Library ]] | Franklin, MA | Completed Sep 1904 | +| 022a | [[P022a |Powerhouse & Pumping Station for City of East Orange, NJ]] | East Orange, NJ | Contract Jun 1904 | 
-| [[P025|025]] | [[P025| Pumping Plant & Tanks for Boston Molasses Co ]] | [[fbglist-geo#boston, massachusetts|Boston]] | 1904 | +| 022b | [[P022b|3-story Store for Lilly Estate]] | [[fbglist-geo#baltimore, maryland|Baltimore, MD]] | Contract Jul 1904 | 
-| [[P026|026]] | [[P026|Factory for Auburn Hame Co]] | [[fbglist-geo#auburn, new york|Auburn, NY]] | Late 1904 | +| 023 | [[P023|Building for DA Sargent/Normal School of Physical Education ]] | [[fbglist-geo#cambridge, massachusetts|Cambridge, MA]] | Completed Aug 1904 | 
-| [[P027|027]] | [[P027|Hydropower Dam on Saranac River]] | Cadyville, NY | 1904-05 | +| 024 | [[P024|Ray Memorial Building / Franklin Public Library ]] | Franklin, MA | Completed Sep 1904 | 
-| [[P028|028]] | [[P028|Two Mercantile Buildings for Rumford Falls Power Co]] | Rumford Falls, ME | 1905 | +| 025 | [[P025| Pumping Plant & Tanks for Boston Molasses Co ]] | [[fbglist-geo#boston, massachusetts|Boston]] | 1904 | 
-| [[P029|029]] | [[P029|4-story Mill for Walworth Manufacturing Company]] | [[[fbglist-geo#boston, massachusetts|Boston]] | < 1905 | +| 026 | [[P026|Factory for Auburn Hame Co]] | [[fbglist-geo#auburn, new york|Auburn, NY]] | Late 1904 | 
-| [[P030|030]] | [[P030|House & Stable for EJ Bliss]] | [[fbglist-geo#boston, massachusetts|Boston]] (Chestnut Hill) | < 1905\\ Probably 1904 | +| 026a | [[P026a|Automobile Garage for A.G. Van Nostrand ]] | [[fbglist-geo#boston, massachusetts|Boston]] | Nov 1904 | 
-| [[P031|031]] | [[P031|Powerhouse & Foundation for Syracuse, Rochester & Eastern RR]] | Lyons, NY | < 1905 | +| 027 | [[P027|Hydropower Dam on Saranac River]] | Cadyville, NY | 1904-05 | 
-| [[P032|032]] [[P032|Automobile Garage]] [[fbglist-geo#boston, massachusetts|Boston]] | < 1905 +| 028 | [[P028|Two Mercantile Buildings for Rumford Falls Power Co]] | Rumford Falls, ME | 1905 | 
-| [[P033|033]] [[P033|7-story Dormitory]] [[fbglist-geo#cambridge, massachusetts|Cambridge, MA]] | < 1905 +| 029 | [[P029|4-story Mill for Walworth Manufacturing Company]] | [[[fbglist-geo#boston, massachusetts|Boston]] | < 1905 | 
-| [[P034|034]] [[P034|Powerhouse for City of East Orange, NJ]] East Orange, NJ | < 1905 +| 030 | [[P030|House & Stable for EJ Bliss]] | [[fbglist-geo#boston, massachusetts|Boston]] (Chestnut Hill) | < 1905\\ Probably 1904 | 
-| [[P035|035]] | [[P035|Factory for Kursheedt Manufacturing Co]] | Brooklyn, NY | Late 1904-05 | +| 031 | [[P031|Powerhouse & Foundation for Syracuse, Rochester & Eastern RR]] | Lyons, NY | < 1905 | 
-| [[P036|036]] | [[P036|Concrete Canal for Lehigh Coal & Navigation]] | Taylorsville, Pennsylvania\\ (now Washington Crossing) | 1905? | +| 032 | See 026a ||| 
-[[P037|037]] | [[P037|6-story plant for John J. Latteman Shoes]] | Brooklyn, NY | 1905 | +| 033 | See 005 ||| 
-[[P038|038]] | [[P038|Plant for Oneida Community Company Ltd]] | Oneida, NY | Jun 1905 | +| 034 | See 022a ||| 
-[[P039|039]] | [[P039|Factory & Warehouse for Walter F Lowney Co]] | Montréal, Québec, Canada | Jun-Aug 1905 | +| 035 | [[P035|Factory for Kursheedt Manufacturing Co]] | [[fbglist-geo#nyc, new york | Brooklyn, NY]] | Late 1904-05 | 
-[[P040|040]] | [[P040|Mill & Mill Town for St. Croix Paper Company]] | Sprague’s Falls, ME\\ (now Woodland/Baileyville) | Contract Feb 1905\\ Construction begun Mar 1905\\ Completed Dec 1905 | +| 036 | [[P036|Project for Houghton County Street Railway]] | Houghton, MI | Early 1904 | 
-[[P041|041]] | [[P041|Mill Buildings & Mill Town for International Paper Co]] | Piercefield, NY | Contract Aug 1904\\ Completed 1905 | +| 037 | [[P037|Concrete Canal for Lehigh Coal & Navigation]] | Taylorsville, PA\\ (now Washington Crossing) | 1905? | 
-[[P042|042]] | [[P042|Dams & Powerhouse for International Paper Co]] | Berlin, NH | 1905 | +038 | [[P038|6-story plant for John J. Latteman Shoes]] | [[fbglist-geo#nyc, new york | Brooklyn, NY]] | 1905 | 
-[[P043|043]] | [[P043|Rail Car Barn & Substation for NY Central Railroad]] | North Syracuse, NY | Contract May 1905 | +039 | [[P039|Plant for Oneida Community Company Ltd]] | Oneida, NY | Jun 1905 | 
-[[P044|044]] | [[P044|Roper Hospital]] | Charleston, SC | Contract May 1905\\ Completion announced Feb 1906 | +040 | [[P040|Factory & Warehouse for Walter F Lowney Co]] | Montréal, Québec, Canada | Jun-Aug 1905 | 
-[[P045|045]] | [[P045|Hydropower Dam for Walter Baker & Co Ltd]] | Milton, MA | Aug 1904 | +041 | [[P041|Mill & Mill Town for St. Croix Paper Company]] | Sprague’s Falls, ME\\ (now Woodland/Baileyville) | Contract Feb 1905\\ Construction begun Mar 1905\\ Completed Dec 1905 | 
-[[P046|046]] | [[P046|Residence for CB Alexander]] | Manhattan, NYC | Late 1904–05 | +042 | [[P042|Mill Buildings & Mill Town for International Paper Co]] | Piercefield, NY | ContractAug 1904\\ 1905 | 
-| [[P047|047]] | [[P047|Barge Canal for Union Sulphur Co]] | Sulphur, LA | Contract Oct 1905\\ //Never completed by FBG// | +043 | [[P043|Dams & Powerhouse for International Paper Co]] | Berlin, NH | 1905 | 
-| [[P048|048]] | [[P048|Factory for Yale & Towne]] | [[fbglist-geo#stamford, connecticut | Stamford, CT]] | 1905 | +044 | [[P044|Rail Car Barn & Substation for NY Central Railroad]] | North Syracuse, NY | Contract May 1905 | 
-| [[P049|049]] | [[P049|Factory for Simmons Hardware Company]] | Sioux City, IA | Contract May 1905 | +045 | [[P045|Roper Hospital]] | Charleston, SC | Contract May 1905\\ Completion announced Feb 1906 | 
-| [[P050|050]] | [[P050|Two Factory Buildings for Yale & Towne]] | [[fbglist-geo#stamfordconnecticut | Stamford, CT]] | 1906 | +046 | [[P046|Hydropower Dam for Walter Baker & Co Ltd]] | Milton, MA | Aug 1904 | 
-[[P052|052]] | [[P052|MIT Naval Engineering Building]] | [[fbglist-geo#boston, massachusetts|Boston]] | Jan-Jul 1906 | +047 | [[P047|Residence for CB Alexander]] | [[fbglist-geo#nyc, new york | Manhattan, NYC]] | Late 1904–05 | 
-| [[P053|053]] | [[P053|10-story McGraw Building (“Engineering Record“)]] | ManhattanNYC | 1906 | +| 048 | [[P048|Building for Yale & Towne]] | [[fbglist-geo#stamford, connecticut | Stamford, CT]] | Apr 1905 | 
-| [[P054|054]] | [[P054|Georgetown Steam Plant (Seattle Electric Lighting Co)]] | Georgetown (Seattle), WA | Construction begun Apr 1906\\ In operation 1907 | +| 049 | [[P049|Warehouses for Simmons Hardware Co]] | Sioux City, IA | Contract May 1905 | 
-| — |  //San Francisco Earthquake & Fire, Apr 1906//  ||| +| 050 | [[P050|Project for Bay Road Construction Co]] | Syracuse, NY | 1905 | 
-[[P055|055]] | [[P055|Mutual Life Insurance Building]] | [[fbglist-geo#san francisco, california | San Francisco]] | 1906-07 +| 050a | [[P050a|Barge Canal for Union Sulphur Co]] | SulphurLA Contract Oct 1905\\ Work until Early Spring 1906\\ //Never completed by FBG// 
-[[P056|056]] | [[P056|Two warehouses for Timothy Hopkins]] | [[fbglist-geo#san francisco, california | San Francisco]] | Contract Jun 1906 | +051 | [[P051|MIT Naval Engineering Building]] | [[fbglist-geo#boston, massachusetts|Boston]] | Jan-Jul 1906 | 
-[[P057|057]] | [[P057|Three Buildings for Henry Sonntag]] | [[fbglist-geo#san francisco, california | San Francisco]] | Contract Jun 1906 | +| 052 | [[P052Paper Mill for Champion Fibre Co]] | Canton, NC | Contract Apr 1906\\ Completed by Jan 1907 | 
-| [[P051|051]] | [[P051|4-story Mill for Minterburn Textile Mills]] | Rockville, CT | Contract Sep 1906\\ Construction begun Oct 1906\\ Completed early 1907 | +| 053 | [[P053|Two Buildings for Yale & Towne]] | [[fbglist-geo#stamfordconnecticut Stamford, CT]] | Apr-Jul 1906 | 
-| [[P058|058]] | [[P058|8-story StClair Building (Boyd Building)]] | [[fbglist-geo#san francisco, california San Francisco]] | Completed Jul 1907 | +| 054 | [[P054|Georgetown Steam Plant (Seattle Electric Lighting Co)]] | Georgetown (Seattle), WA | Construction begun Apr 1906\\ In operation 1907 | 
-| [[P059|059]] | [[P059|North Beach Electric Power Station for City Electric Co]] | [[fbglist-geo#san franciscocalifornia San Francisco]] | In operation Oct 1907 +055 | [[P055|10-story McGraw Building (“Engineering Record“)]] | [[fbglist-geo#nyc, new york | Manhattan, NYC ]] | 1906 | 
-[[P060|060]] | [[P060|Citizen’s Bank of Alameda]] | AlamedaCA 1907 +|  —  |  — //[[sf1906 | San Francisco Earthquake & Fire, Apr 1906]]// —  |||  
-[[P061|061]] | [[P061|7-story Wilson Building]] (rebuild) | [[fbglist-geo#san francisco, california | San Francisco]] | 1907-08 | +056 | [[P056|North Beach Electric Power Station for City Gas & Electric Co]] | [[fbglist-geo#san francisco, california | San Francisco]] | Contract May 1906\\ In operation Oct 1906 | 
-[[P062|062]] | [[P062|4-story Union Square Hotel]] | [[fbglist-geo#san francisco, california | San Francisco]] | ca. 1907 | +057 | [[P057|Two Warehouses for Timothy Hopkins]] | [[fbglist-geo#san francisco, california | San Francisco]] | Contract Jun 1906 | 
-[[P063|063]] | [[P063|5-story Pacific Grand Hotel]] | [[fbglist-geo#san francisco, california | San Francisco]] | Opened July 1907 | +058 | [[P058|Three Buildings for Henry Sonntag]] | [[fbglist-geo#san francisco, california | San Francisco]] | Contract Jun 1906 | 
-[[P064|064]] | [[P064|Plant for Pennsylvania Cement Company]] | //Unknown// | 1907 | +| 059 | [[P059|St. Clair Building (aka Boyd Building)]] | [[fbglist-geo#san francisco, california | San Francisco]] | Contract Jun 1906\\ Completed Jul 1907 | 
-| [[P065|065]] | [[P065|Mill for Champion Fibre Co]] | CantonNC Contract ca. Mar 1906\\ Completed by Jan 1907 | +| 060 | [[P060|Mutual Life Insurance Building]] | [[fbglist-geo#san francisco, california | San Francisco]] | Contract Sep 1906\\ 1907 | 
-[[P066|066]] [[P066|Mill for Champion Coated Paper Co]] | Hamilton, OH | Contract Sep 1906\\ 1907 +| 061 | [[P061|4-story Mill for Minterburn Textile Mills]] | Rockville, CT | Contract Sep 1906\\ Construction begun Oct 1906\\ Completed early 1907 | 
-[[P066a|066a]] | [[P066a| Foundry & Forge Shop for Stayman Manufacturing Co ]] | Jersey City, NJ | In progress Sep 1906 | +| 062 | [[P062|Citizen’s Bank of Alameda]] | Alameda, CA | Contract Sep 1906\\ Completed Apr 1907 | 
-| [[P067|067]] | [[P067|Power Station for Plymouth and Brockton Street Railway]] | Plymouth, MA | 1907 | +| 063 | [[P063|2-story Mill for Henry MCrane]] | Bayonne, NJ | Contract Sep 1906 | 
-| [[P068|068]] | [[P068|Power Station for Blue Hill Street Railway]] | Canton, MA | 1907+| 064 | [[P064|Mill for Champion Coated Paper Co]] | Hamilton, OH | Contract Sep 1906\\ 1907 | 
-[[P069|069]] | [[P069|3-story Factory Addition for Columbian Rope Co]] | [[fbglist-geo#auburn, new york|Auburn, NY]] | 1907 | +| 065 | [[P065Forge & Machine Shop for Stayman Manufacturing Co ]] | Jersey City, NJ | Contract Sep 1906 | 
-| [[P070|070]] | [[P070|Two Factory Extensions for Yale & Towne]] | [[fbglist-geo#stamford, connecticut | Stamford, CT]] | Contract Apr 1907 | +| 066 | [[P0662-story Building for Stayman Manufacturing Co ]] | Jersey CityNJ Contract Oct 1906 
-[[P071|071]] | [[P071|5-story Factory for S.L. Allen & Co]] | Philadelphia, PA | Contract Feb 1907 | +067 | [[P067|Warehouse for BF Goodrich]] | AkronOH Contract Oct 1906\\ Completed Dec 1906 
-| [[P072|072]] | [[P072|“Fenimore” Paper Mill for Union Bag and Paper Co]] | Glen’s Falls, NY | 1907+068 | [[P068|7-story Wilson Building]] (rebuild) | [[fbglist-geo#san francisco, california | San Francisco]] | 1907-08 | 
-| [[P073|073]] | [[P073|Factory for H.C. White Co]] | North Bennington, VT | Contract Nov 1907 | +069 | [[P069|Union Square Hotel]] | [[fbglist-geo#san francisco, california | San Francisco]] | Contract Jan 1907\\ Opened Jan 1908 
-[[P074|074]] | [[P074|Factory for Heywood Brothers & Wakefield Co]] | Gardner, MA | Contract Jun 1907\\ Construction Mar 1908 | +070 | [[P070|Pacific Grand Hotel]] | [[fbglist-geo#san francisco, california | San Francisco]] | Contract Jan 1907\\ Opened July 1907 | 
-| [[P075|075]] | [[P075|Can Factory for Seacoast Canning Company]] | Eastport, ME | Contract Feb 1908 | +071 | [[P071|Plant for Pennsylvania Cement Company (?)]] | BathPA | 1907 | 
-[[P076|076]] | [[P076|Shoe & Leather Exposition Building]] (completion) | [[fbglist-geo#boston, massachusetts|Boston]] | Contract May 1908 | +072 see 007a ||| 
-[[P077|077]] | [[P077|Two Warehouses for New England Confectionery Company (NECCO)]] | [[fbglist-geo#boston, massachusetts|Boston]] | Probably 1907 (< 1909) +073 | [[P073|Power Station for Blue Hill Street Railway]] | Canton, MA | 1907 | 
-[[P078|078]] | [[P078|Project for W.M. Crane Paper Co]] | [[fbglist-geo#dalton, massachusetts| Dalton, MA ]] | < 1909 | +074 | [[P074|3-story Factory Addition for Columbian Rope Co]] | [[fbglist-geo#auburn, new york|Auburn, NY]] | Contract Apr 1907\\ Completed Dec 1907 | 
-[[P079|079]] | [[P079|Project for Dalton Power Co]] | [[fbglist-geo#dalton, massachusetts| Dalton, MA ]] | < 1909 | +075 | [[P075|5-story Factory for S.L. Allen & Co]] | Philadelphia, PA | Contract Feb 1907 | 
-[[P080|080]] | [[P080|Project for Columbia Electric Vehicle Co]] | [[fbglist-geo#boston, massachusetts|Boston]] | < 1909 | +| 076 | [[P076|Two Warehouses for New England Confectionery Co (NECCO)]] | [[fbglist-geo#boston, massachusetts|Boston]] | Contract ~Apr 1907\\ Completed ~Aug 1907 | 
-[[P081|081]] | [[P081|Project for Boston Steam & Power Co]] | [[fbglist-geo#boston, massachusetts|Boston]] | < 1909 | +| 077 | [[P077|Two Building Extensions for Yale & Towne]] | [[fbglist-geo#stamford, connecticut Stamford, CT]] | Contract Apr 1907 | 
-[[P082|082]] | [[P082|Project for the Lowell Bleachery Co]] | Lowell, MA | < 1909 | +078 | [[P078|Factory for Heywood Brothers & Wakefield Co]] | Gardner, MA | Contract Jun 1907\\ Construction Mar 1908 | 
-[[P083|083]] [[P083|Project for Houghton County Street Railway]] | Houghton, MI | < 1909 +| 079 | See 097 ||| 
-[[P084|084]] | [[P084|Project for Bay Road Construction Co]] | Syracuse, NY | < 1909 | +| 080 | [[P080|Factory for H.C. White Co]] | North Bennington, VT | Contract Nov 1907 | 
-| [[P085|085]] | [[P085|Paper mill for H.G. Lowe Paper]] | Ridgefield, New Jersey | < 1909 | +| 081 | [[P081|Can Factory for Seacoast Canning Company]] | Eastport, ME | Contract Feb 1908 | 
-[[P086|086]] | [[P086|1-story Extension to Cotton Mill for H.E. Danner Textile Co]] | Paterson, New Jersey | Contract Jul 1908\\ Construction begun Dec 1908\\ Probably completed Feb 1909 | +082 | [[P082|Shoe & Leather Exposition Building]] (completion) | [[fbglist-geo#boston, massachusetts|Boston]] | Contract May 1908 | 
-[[P087|087]] | [[P087|Box Plant for Atwood-McManus Co]] (reconstruction) | [[LOCchelseama|Chelsea, MA]] | Dec 1908-Mar 1909 | + —   //— [[1909block * Projects in this block are unconfirmed and may be as early as 1904]] —//  ||| 
-[[P088|088]] | [[P088|Hydroelectric Powerhouse for Grand Falls Power Co]] | Grand Falls, NB/ME\\ (international river border) | Contract Mar 1909\\ //Never completed// | +083 | [[P083|Project for Z. & W.M. Crane Paper Co]] | [[fbglist-geo#dalton, massachusetts| Dalton, MA ]] | < 1909 | 
-| [[P089|089]] | [[P089|Ransom Hollow Dam & Powerhouse for Warren County Power Co]] | Columbia, New Jersey | Contract Oct 1909 | +084 | [[P084|Project for Dalton Power Co]] | [[fbglist-geo#dalton, massachusetts| Dalton, MA ]] | < 1909 | 
-[[P090|090]] | [[P090|Ransom Hollow Dam & Powerhouse]] | Creighton, GA | Contract Feb 1910 | +085 | [[P085|Project for Columbia Electric Vehicle Co]] | [[fbglist-geo#boston, massachusetts|Boston]] | < 1909 | 
-[[P090a|090a]] | [[P090a | 4-story Apartment Building for Isaac Wrubel ]] | Paterson, NJ | Contract Feb 1910 | +086 | [[P086|Project for Steam & Power Co]] | [[fbglist-geo#boston, massachusetts|Boston]] | < 1909 | 
-[[P091|091]] | [[P091|Paper Mill for Union Bag & Paper Co]] | Trois-Rivières, Québec, Canada | Contract Sep 1910\\ In service early 1912 |+087 | [[P087|Project for the Lowell Bleachery Co]] | Lowell, MA | < 1909 | 
 +088 See 049a ||| 
 +089 | [[P089|Paper mill for H.G. Lowe Paper]] | Ridgefield, NJ | < 1909 | 
 +090 | [[P090|1-story Cotton Mill Extension for H.E. Danner Textile Co]] | Paterson, NJ | Contract Jul 1908\\ Construction begun Dec 1908\\ Completed early 1909 | 
 +091 | [[P091|Box Plant for Atwood-McManus Co]] (reconstruction) | Chelsea, MA | Dec 1908-Mar 1909 | 
 +092 | [[P092|Hydroelectric Powerhouse for Grand Falls Power Co]] | Grand Falls, NB/ME\\ (international river border) | Contract Mar 1909\\ //Never completed// | 
 +| 092a| [[P092aFishing Pier for H.F. Kean]] | Sandy Hook, NJ | Mar-Apr 1909 | 
 +| 092b| [[P092b| Frost Building]] | Plainfield, NJ | Contract Sep 1909\\ Completed Jan 1910 | 
 +| 093 | [[P093|Ransom Hollow Dam & Powerhouse for Warren County Power Co]] | Columbia, NJ | Contract Oct 1909 | 
 +094 | [[P094|Ransom Hollow Dam & Powerhouse]] | Creighton, GA | Contract Feb 1910 | 
 +095 | [[P095| 4-story Apartment Building for Isaac Wrubel ]] | Paterson, NJ | Contract Feb 1910, Completed 1910 | 
 +096 | [[P096|Paper Mill for Union Bag & Paper Co]] | Trois-Rivières, Québec, Canada | Contract Sep 1910\\ In service early 1912 
 +| 097 | [[P097| Addition to “Fenimore” Paper Mill for Union Bag & Paper Co]] | Glen’s Falls, NY | Contract Feb 1911\\ Completed Jun 1911 |
  
  